The Client

The client is a leading drug development company with facilities spanning across more than 60 different countries.

The Challenge

The client reached out to EquipNet seeking assistance to empty a facility of 40,000 sq ft in 3 weeks as their lease was due.

Equipment at this site included various type of equipment, such as Bio Safety Cabinets, Laboratory Equipment, Tanks and other processing pharmaceutical equipment.

The Solution

Since there was a very tight deadline to empty the entire facility, EquipNet made an offer for the entire facility for immediate financial return.

The Result

EquipNet achieved full clearance within the client’s requested deadline. Despite the obstacles EquipNet had to overcome, the client was very satisfied with the results of the project.

Highlights
Challenge
Empty a facility of 40,000 sq ft

Timeframe
3 weeks

Equipment Categories
Bio Safety Cabinets
Laboratory Equipment
Tanks
Processing Pharmaceutical Equipment

Services
Outright Purchase Program

Interested in Learning More About Our Services?